M-13.1, r. 1 - Regulation respecting petroleum, natural gas and underground reservoirs

Full text
121.1. The holder of an authorization to produce brine pays the following fees on brine extracted from the site under the authorization:
(1)  where the average daily production per producing well is 300 m3 or less, 5% of the market value at the wellhead of the substance extracted from the brine;
(2)  where the average daily production per producing well is greater than 300 m3 but less than 1,000 m3,
(a)  5% of the market value at the wellhead of the extracted substance on the first 300 m3;
(b)  10% of the market value at the wellhead of the extracted substance on the remainder;
(3)  when the average daily production per producing well is greater than 1,000 m3,
(a)  8.75% of the market value at the wellhead of the extracted substance on the first 1,000 m3;
(b)  12.5% of the market value at the wellhead on the remainder.
O.C. 1381-2009, s. 60.